New Metro Line B in Rennes: Viaduct is planned with TILOS

The New Metro Line B in Rennes contains a big viaduct. It is build from Eiffage and planned with TILOS.

  • Total length : 14 km
  • Tunnel Section : 7,5 km
  • Viaduct : 2,8 km
  • Stations : 15
  • Estimated cost (value 01/2010) : 1194 Million Euro
    (Source: http://metropole.rennes.fr/politiques-publiques/grands-projets/ligne-b-de-metro-le-projet/)


Our french partner Projet linéaire is supporting the TILOS usage.

The Metro Line B will be run with an automatic Metro System VAL (Véhicule automatique léger)

By Pline (Own work) [GFDL (http://www.gnu.org/copyleft/fdl.html) or CC BY-SA 3.0 (http://creativecommons.org/licenses/by-sa/3.0)], via Wikimedia Commons

Rennes Metro: Train type Val208

 

(931)

How to prepare a Primavera Schedule for Exporting to TILOS Time Location System

Following a description of the most basic preparations on a Primavera Schedule, when you intend to transfer this Schedule to TILOS and display it in a Time-Location-Diagram:

Promavera To TILOS

A. Additional Data Fields

Some additional information for the activities has to be edited in the Primavera project:

  1. Location information
    Each activity needs to have a Start Location and End Location value. Those are needed to display the activity along the location axis and this is displaying the working direction too.
    Preparation: Create User Defined Fields (Text) named StartLocation and EndLocation and insert the corresponding values.
  2. Display information (Colors and shapes)
    In the Time-Location diagram a task cannot only be displayed in one fixed way: They can have different shapes (e.g. lines, rectangles, parallelograms), linestyles and color. Those graphical characteristics are in TILOS controlled by the object “template”.
    Preparation: Create a User Defined Field (Text) named TilosTemplate and insert for each activity a value (e.g.”pipe laying” or “concrete work”): All activities that should look the same in TILOS get the same value.

B. Activity Filter

Preparation: Create a Filter that selects all the activities that you want to transfer. You may create another User Defined Field (Text) named TilosExport and set a value when the Activity should be exported.

Think about Structures, Summaries and Granularity:
Is the Time-Location diagram showing all details or is there a different Granularity? E.G. Some Buildings/construction elements can be displayed by the Summary activity only. In this case Summary/WBS activities or level of effort activities has to be created.

Define the task granularityDownload this description as a PDF

 