TILOS 8 brings day durations on calendar level

As up to Version 7 the day duration unit was controlled in a general setting for ALL tasks in the project – and so you have to use the the same day duration for all tasks.

In TILOS 8 there is a day duration controlled by the calendar: In each calendar you may define a day duration fitting to that specific calendar.

Sample: 24-hrs-day for tunnel driving tasks or 10-hrs-days for earthwork.

calendar definition expanded

As a result each task using that certain calendar displays its duration from its assigned calendar.