How to prepare a Primavera Schedule for Exporting to TILOS Time Location System

Following a description of the most basic preparations on a Primavera Schedule, when you intend to transfer this Schedule to TILOS and display it in a Time-Location-Diagram:

Promavera To TILOS

A. Additional Data Fields

Some additional information for the activities has to be edited in the Primavera project:

  1. Location information
    Each activity needs to have a Start Location and End Location value. Those are needed to display the activity along the location axis and this is displaying the working direction too.
    Preparation: Create User Defined Fields (Text) named StartLocation and EndLocation and insert the corresponding values.
  2. Display information (Colors and shapes)
    In the Time-Location diagram a task cannot only be displayed in one fixed way: They can have different shapes (e.g. lines, rectangles, parallelograms), linestyles and color. Those graphical characteristics are in TILOS controlled by the object “template”.
    Preparation: Create a User Defined Field (Text) named TilosTemplate and insert for each activity a value (e.g.”pipe laying” or “concrete work”): All activities that should look the same in TILOS get the same value.

B. Activity Filter

Preparation: Create a Filter that selects all the activities that you want to transfer. You may create another User Defined Field (Text) named TilosExport and set a value when the Activity should be exported.

Think about Structures, Summaries and Granularity:
Is the Time-Location diagram showing all details or is there a different Granularity? E.G. Some Buildings/construction elements can be displayed by the Summary activity only. In this case Summary/WBS activities or level of effort activities has to be created.

Define the task granularityDownload this description as a PDF

 

(1209)

How to import activities to TILOS from a simple Primavera Excel-Output

Primavera P6 allows to put activity data in an Excel Spreadsheet. This small guide is showing how to set up the TILOS Excel import profile in order to create a TILOS chart fast and easy.

1. Preparation

a. Location information:
In Primavera create the activity user defined fields “FromLocation” and “ToLocation”. For each activity in question fill the location values. (e.g.12’580).

b. Template information (Display of the TILOS tasks)
One activity field is necessary to contain the TILOS task template information in order control the display of the task in TILOS.  You may use codings that are containing all names of the TILOS task template. (e.g Code “Welding”, that points to the task template “Welding” in TILOS.)

c. activity selection (Filter)
In most cases not all activities shall be transported. Please use a filter to select the activities to export.

d. Export to Excel file
For Primavera output use the predefined P6 activity fields and add the user defined fields for template code and FromLocation and ToLocation.
The Output file looks similar to that sample: On the page “TASK” you find some columns containing you activity data. The table has two headlines.
(You may also export the Links in the Excel file. In this case for links there will be a page “TASKPRED”.)

Primavera Excel Export

e. Prepare the TILOS file
Adjust the Time-Distance-Diagram to show the time and distance range fitting to the activity data.
Approve, that all activity templates are existing and the display is set up correctly

 2. Importing into TILOS

  • In  TILOS choose “File -> Import” to call the Import Wizard.
  • Import Wizard Step one (Import format): Choose “Microsoft Excel (XLS)” (Note: You have to licene that module)
  • Import Wizard Step two (Data source): Select the xls file that cotains the data.
  • Import Wizard Step three: (Select profile): Select the template profile “Primavera Import Sample WBS as Task field”.
    Once you have to change the profile to match your spreadsheet. Later you may reuse it.

Here are some important hints:
The Format m/d/yyyy h:nn:ss AM/PM describes the Standard US date formatting Primavera uses for the dates.You may adjust that to your local settings.
TILOS Import: Formatting

Number 3: Edit the activity field list used in the spreadsheet. The fields and the number of the columns in the spreadshee has to match:

TILOS Import, Fieldlist

  • Import Wizard Step four (Sub-Project selection):  Choose the subproject the data should be inserted in.

During the import the Wizard is doing.

  • Creating each line as a task with the desired field values
  • Assigning the Template (Display) for each task
  • Checking the Task-Id: if this task is already existing there will be no new task created. Only the values will be updated on the existing task

 