What is New in TILOS 8: In details

wint8

Increased Speed – More Capacity – Greater Flexibility

TILOS 8 was developed with a new kernel providing the technology for rapid future developments in the coming years.

We have also made many evolutionary little feature enhancements that are not specifically mentioned, but makes working in TILOS 8 a lot easier and comfortable.

Usability

Zooming: The zoom of a view can be directly modified by pressing the control button and using the mouse wheel.

Scrolling: The horizontal scroll position can be changed by pressing the shift button and using the mouse wheel.

Auto scrolling: When creating links or sizing tasks and moving the mouse towards the border of the working windows, the view starts scrolling to make further objects visible.

Multiple instances: TILOS can be started multiple times with different projects. Using drag and drop with the mouse allows data to be copied directly from one project to another. (see: Drag & Drop below)

 

Architecture

Speed enhancements: TILOS 8 uses multiple processors/threads to execute the code in parallel. For example: While reschedule runs, you may be edit objects.
Loading projects is up to 20 times quicker, reschedule up to 50 times – as well as importing and exporting data.
Loading grouped and sorted Gantt charts shows up to 100 times quicker.

Tables and Lists: The tables (grids) and the list boxes have been re-engineered to work much faster than before in terms of loading, scrolling and sorting. Each column can be used for sorting by clicking on the column header.grid
Any column can be locked and only the columns to the right of this are scrolled. This can be done by right-clicking on the column heading and locking the columns to the left.
The whole list can be copied to the Windows clipboard – by right-clicking on any column header.

Multi-edit: Multiple rows (max 500) can be selected and any edits on the Properties Tabs will multi-edit the same data item on all selected items.
Tree structures (task templates) can be moved by drag and drop to change the parent items. In simple lists items can be copied by dragging them.

Drag & Drop: If two or more TILOS projects are opened at the same time, data can be copied between the two TILOS instances. This works based on the tables (grids), not in the time distance view.drag
All library items as well as activities can be moved/copied in that way. Missing library items in the destination file are automatically created, if they do not exist in the destination file. For simple items (“other” library objects and graphic)., the “already-exists”-check is done by the name  Other items, like task templates, resources or calendars are identified by their ID.
If tasks are copied between sub projects, all new items are created with a new TASK ID.
If a whole sub project is dragged between TILOS instances the behavior is different: If a sub project with the same ID is existing in the destination file, then its tasks will be replaced completely by the sub project that is copied.  In this case, tasks in the destination project keep their old Task ID from the source file.
This function allows to merge different sub projects into one destination file.

 

Explorer view

The explorer has now three main folders to simplify the navigation:

Views: In the VIEWS-folder all views are grouped by view type. The result is a better exploreoverview as all data views are grouped in one place. (The task and link list  of version 7 have been moved from sub project context to an own view type in view folder).
Views can be sorted and grouped by type or user defined values.
A few new list views have been defined such as the Micro Progress View, that displays all the micro progress records of a project.

Project data: All project specific data is stored in this folder. In earlier versions of TILOS those have been partly located in library folder. Now there is a good separation between project specific data and general library data.

Library: This contains base data not necessarily linked to one specific  project –  such as task templates, resource and cost library.

Time distance view

Cell wizard: The new cell wizard supports all types of cell content to embed existing cell contents or to create new cell contents in order to view them in a cell. Cell and View setup is more easy and intuitive now.

Multi sub projects: Up to TILOS 7 one time-distance cell could display only 1 sub project. In TILOS 8 now multiple sub projects can be added to be displayed the same time-distance cell. Planning and viewing of data is now more flexible:

  • Different scenarios can be overlaid in order to compare them.
  • Parts of the project can be planned in separate TILOS files from different persons, merged and then overlaid to highlight the interaction between the different planning states.

Gantt Chart Output

Grouping and sorting: The grouping and sorting options for the Gantt chart view have been enhanced and is much faster in TILOS 8. Different views can be created and saved for later use.

Print to multiple pages: Large projects can be printed to multiple pages by enveloping them to a definable border view around each page of the output.

Hide bars panel: This options allows us to only print the Gantt chart text panel without the gantt bars, For example as a project summary report list with progress and earned value data.

Enhanced Controlling features

Baseline: In TILOS 7 baselines were created at the sub project level and each baseline baselinehad its own report date. This has been unified in TILOS 8 and the baselines are now global for the whole project.
Newly introduced tasks can be added to existing baselines as an update. Different baselines can be merged to one baseline after conversion from Version 7.
This allows more powerful reports and progress analysis in time distance diagrams where different sub projects are merged in one view.

histoHistograms: Histograms can display baseline data in TILOS 8 in order to compare them with the original planned values.
The main advantage is to analyze the planned and achieved productivity during execution phase.
Cumulative curves have a new option to draw the lines and show the data only up to the report date.

Dashboard: The dashboard showing performance and earned value data from different crews can now be embedded into a cell of the time distance view.
dashboard

Mass Haulage

 

Overview: This is a completely new functionality added to TILOS 8 and is designed for heavy civil works. It supports a multistep planning of mass transportations. After importing the quantities and the areas, the haulage itself and the sequencing can be planned more easily and smart.

Mass Diagram: The mass haulage diagram displays all quantities (mass areas) along the distance axis referring to a soil type table.
The diagram displays the main cut and fill areas, borrow pits, dump sites and stockpiles.

mass diagram Histograms: Based on the mass areas, diagrams can be defined using TILOS standard functionality:

Cumulative quantity curves showing total cut and fill values and balanced curves preparing the haulage are available. The shortest transports are between the zero line of the balance curve indicating equal cut and fill situation.

mass histogramHaulage planning: Planning the haulage is interactively done by drawing connectors between the mass areas. On the fly the transport distance and the cut / fill state of each area is analyzed and displayed.

haulage planningScheduling: By a wizard you may create from the haulage lines the cut and fill tasks in the time distance diagram. After adding the links, the reschedule process can be activated to calculate the required time for the mass haulage and also the time based usage of the equipment in the diagrams.

haulage schedulingControlling: The Mass haulage controlling uses the standard reporting function of TILOS. Different progress methods can be used: Direct progress entry or micro progress can be imported. Evaluation is also using the standard functionality of TILOS.

haulage controlling

Data Exchange

General enhancements: The XML profile editor has been integrated into TILOS and it is located in the Tools menu option.
When creating a data file, the XML profile information can be embedded  in that data file. This simplifies the import by using the embedded profile.
Additional to transfer data by creating a data file, the data exchange in TILOS 8 can directly connect TILOS to the Exchange macros via a TCP-IP based connection.

MS Project: Support for MS Project 2013 has been added.

Primavera: Support for WBS structure that can be exchanged with TILOS directly.

iTWO: A new module has been developed to exchange data with the RIB iTWO software.

It can import the activitiy model with assigned resource and cost from RIB iTWO. In the reverse way, the TILOS activity model can be exported to iTWO.
This allows creating the schedule in TILOS and export to iTWO to make the connection with the estimate. The resource loaded schedule can be passed back to TILOS updating the existing activities.

Other enhancements

wbsWBS Structure: In addition to category structures, a WBS structure can be created and   applied to the tasks. This can be used for grouping the data in the Gantt chart based on the WBS code.

 

 

duration displayDuration display: For each calendar a base time unit can be defined to show working days in relation to the working time defined in that specific calendar. (e.g. 8h days, 10h days depending on the defined working time).

 

Distance profiles: More text and user definable data fields have been added.

linestylesLine styles: Viewing task progress in TILOS 7, the progress line styles have been overlaid with the line style of the task. In TILOS 8 this can be placed behind the task.

customizecolors

 

Using the enhanced display mode (Customize colors for progress) for each task, a task individual definition for color and line style can be made for: planned, performed and baseline state of a task.

 

 

(2890)

Copenhagens “Nordhavnsvej” planned with TILOS

The biggest road project of the Copenhagen Municipality is currently under construction. The Nordhavnsvej is a link between Nordhavn and Helsingørmotorvejen. The new road will pass through densely populated areas and will also have to pass under two heavily frequented railway lines and major road intersection.

The consortium between Pihl & Son A.S. / Züblin AG is using TILOS for planning and controlling the overall site and to display and to communicate the processes and the logistic conditions, to those responsible for execution on  one hand and to the project owner on the other hand.

“TILOS is one of our most valuable and essential tools, that helps us displaying the key processes of the complex schedule with lots of different conditions and side-effects when building Nordhavnsvej.

Besides the scheduling possibilities the strength of TILOS is the display: It allows us to explain directions of activities and the effects of activities aside inclusive logistic and mass inspections. With that display we can explain the whole construction process much easier, than with other tools.

This means: Unlike to a Gantt chart diagrams the involved persons are really working with the TILOS schedule and accepting it.

Additionally we plan and control the costs of machine effort and material consumption for the most expensive processes. As we periodically update the plan, we have a very good view of the project, its development and future outlook.”

says Carsten Lehman, responsible for planning and controlling Nordhavnsvej.

At the moment one of the most important steps taking place at the site: In a four weeks full closure of one railway line the trench excavation for the road beneath the train lines has started. After these four weeks the railway line will resume its normal schedule – then based on steel bridges over the trench. Following this, the construction pit will be excavated up to 20m deep – under full rail traffic.

The picture is showing the current state of the site, highlighting the run of the planned underpass.

 