TILOS Task Calculation Part 1: Linear calculation models (Video blog)

This video blog / tutorial is showing some easy linear calculation models, that TILOS Linear Scheduling system uses to estimate task durations.

This is the start of a series of videos regarding TILOS task calculation.

This time:

  • Determining the Work rate = Quantity / Duration
  • Estimating the Duration = Quantity / Work rate

Video:


This video ist hosted by youtube. please change to the best resolution availlable in the bottom settings bar.
(Direct Link to video: http://youtu.be/C8UqKIblCRk)

 TILOS Task Calculation Series:

TILOS Task Calculation Part 1: Linear calculation models (Video blog)

(1146)

Video blog: Displaying different projects with different distance scales on one page

See how to create a second Time-distance-diagram, that contains a different project. That method can be used either for showing separate distance areas in one project but also to display different stages of the same project: Displaying the main schedule and a scenario schedule on one page.

Video:


This video ist hosted by youtube. please change to the best resolution availlable in the bottom settings bar.
(Direct link to the video: http://youtu.be/sdE0xfJc6ow)

(2470)

How to set up tasks with transparent background – for displaying overlapping tasks?

Sometimes you need to display multiple tasks at the same place – or need to overlap each other. TILOS has the possibility to use transparent colors, that support the desplay of overlapping tasks. The transparent color can be set not only as a solid background color but also as a transparent part of a pattern.

Take the tagged color from the color picker to select the transparent color:

 

 

 

Create different looking transparent task shapes:

Addition:

Use the object order and the layer order additionally to order the tasks and get the desired look by this way.

 

(1307)

Project Sample: Diversion of Canal Zuid-Willemsvaart

We just received another Time-Location Chart from VolkerWessels to present it on our Website:
It shows the planning of the diversion of a Canal, Section Zuid-Willemsvaart in the Netherlands. In this construction project seveal bridges and buildings along the canal has to be build ior rebuild before the actual work on the canal can be done.
The chart combines a map of the canal, the time-location chart showing the schedule and an elevation diagram showing the land levels combined with the water gauge and embarkment height along the distance.
It is planned to open the new building for shipping end of 2014.

Download the PDF Sample Chart: http://tilos.org/fileadmin/downloads/doc/samples/TWD-Canal.pdf
More Informations: Rijkswaterstaat
More Pictures: Bing Picture Search