When is the crew arriving at a special location?

Mission: Display the date, that a crew/activity is arriving at a special station

Sample application: A pipeline crew is working along the ROW. When is the crew arriving at the river?

Implementation:

  • Create a milestone task at each station you like to have the arrival date/time
  • Link the line activity start/finish to each milestone
  • Select the link option “Calculate lag by Distance tu Successor with the lag value 0. This will force the milestone nearest to the line
  • Add annotations to the milestones and set up the with tokens:

Station: {Start.Distance.Estimate}m
Arriving: {Start.Date.Estimate}

Result after Reschedule:

Addition:

  • The symbol of the milestones can be set in the tab display of the task
  • The size of the milestones can be set in the tab  display of the time-distance cell
  • Station List as a Gantt spreadsheet: